Under Construction – KSQ Barn/Carriage Shed Update 2

HJLCMS has been very busy finishing up the KSQ Barn/Carriage Shed. The last update ended with the exterior being prepared for the siding and the installation of the standing seam metal roof. However, before the siding could go on, the windows had to be installed and the electric had to be run. Once the windows were in and the electric had been run, the siding could be installed. The material for the exterior finish is rough sawn board and batten for the first story and a cedar shake for the second story, upper gables and cupola. While this was going on, one of the HLTF crew members was building the cupola in our shop. The cupola was then transported to the job site where it was finished with cedar shakes and standing seam metal roofing.  This cupola is not solely ornamental, as it will function as passive climate control as well as house the ventilating fan. The cupola was then flown into place with the crane. Check back for the next update.